On Going

 

 

 

 

PROJECT NAME DISTANCE (Km) CONTRACTOR STATUS  COUNTY COST KSH
Construction of Upper Hill – Mbagathi Link Road 11 Interways Construction Co. 38.2% Nairobi                  1,249,921,540.63
Rehabilitation & Upgrading of Old Nairobi road and Bishop Muge 8.5 Dittman Construction Company 35% Uasin-Gishu 684,976,833.20
Rehabilitation & Upgrading of Eastlands Roads Phase II 10 Wak Construction Limited 25.2% Nairobi 1,111,111,222.32
Rehabilitation & Upgrading of Eastleigh Estate Access roads 3 Baraki International Limited 55% Nairobi 552,976,811,10
Rehabilitation of Mathare Roads 8 Tinfra Engineering Ltd 90% Nairobi 95,688,170,90
Rehabilitation and Upgrading of UpperHill Roads, Phase I 5 Mattan Construction 98.3%
Substantially Complete (under defects liability period)
Nairobi      2,002,892,599.00
Construction of Nairobi Eastern Missing Link Roads and Non-Motorised Transport (NMT) Facilities In Nairobi 17.2  Reynolds Construction Company  69.5% Nairobi      4,578,162,618.04
Nairobi Outering Road Improvement Project 13  Sinohydro Construction Company 91.6% Nairobi      7,395,183,298.13
Construction to Bitumen Standards of Meru Bypass Roads 23 H-Young (EA)Limited  53.0% Meru      2,391,755,277.10
Construction to Bitumen Standard of Ngong Road – Kibera – Kungu Karumba – Langata Road (Missing Link No. 12) 4.2 H. Young (EA )Ltd 71% Nairobi      2,097,520,695.00
Construction to Bitumen Standard of Waiyaki Way – Redhill Link Road 5 China Wu Yi Ltd  74.5% Nairobi      3,012,205,102.71
Upgrading to Bitumen Standards of Githurai –Kimbo Road (Phase II) 2  Dickways Construction Ltd  91% Kiambu          423,184,731.00
Upgrading to Bitumen Standards of Eastlands Roads Phase I 5.2  Tosha Holdings  97% Nairobi          347,142,134.06
Rehabilitation and Upgrading of Eastleigh Roads Phase II 3  H-Young Limited  94.3% Nairobi          677,078,139.00
Construction of Annex Loop Roads and Upper Elgon View Loop Roads in Eldoret Town 10  Dittman Construction Company  97% Nairobi          426,132,768.60
Upgrading to Bitumen Standards of Kinunga – Kamuyu Road Phase II 3.8 Territorial Works Ltd  95% Nyeri          237,785,753.75
Rehabilitation and Upgrading of Upper Hill Roads Phase II 6.5  Tosha holdings 47.4% Nairobi      2,258,531,258.11
Upgrading to Bitumen standards of Syokimau – Katani Road Phase II 3.5  Sivad Construction Co Ltd 95.5% Machakos          425,053,087.00
Construction of a Flyover Bridge Across the Northern Bypass and Approaches at Kahawa West 2  Frontier Engineering Limited  77% Nairobi          403,440,924.00
Construction of Lenana – Muchugia road 7 Jomwak Enterprises 85.3% Nairobi                     513,177,612.75
Upgrading of Industrial Area Roads Phase I 4.2 El Adi Construction Co. Ltd 95% Nairobi                     153,053,258.82
Construction of Access Road to Ruai Police Station 1 Wak Construction Ltd 96% Nairobi          132,888,629.37
Upgrading to Bitumen Standards of Mlolongo – Kware – Katani Link Road (Phase I) 6  Ogle Construction Co. 33% Nairobi      1,629,487,068.99
Dualling of Ngong Road (Dagoretti Corner-Karen Roundabout Section) 9.8 China Qingjian Int. Group Ltd  23% Nairobi      1,987,981,992.5
Construction of Kisii Bypass (Phase I) 5.2 Signon Corp. Ltd 18.3% Kisii 448,808,373.60
Construction of Nyahururu Bypass 8 Hanamal Construction Limited 11.8% Laikipia 562,127,004.00
Construction of Kericho Bypass (Phase I) 5 Terrad Construction Ltd 16% Kericho 445,786,294.80
Construction of Kenyatta University Footbridge over Railway Line N/A China Wu Yi Ltd 75%% Kiambu 281162084.7
Construction of Access to Embakasi (Infinity) Industrial Park (Phase II) 2 El Adi Co. Ltd Commencing Nairobi 142,992,028.1
Construction of Kangundo Road – Greater Eastern Bypass Link Road 10 China Aerospace Construction Group (Kenya) Corporation Ltd. Commencing Nairobi 1,160,691,029.4
Construction of Kahawa Sukari Estate Access Roads 6.1 Interways Construction Co. Commencing Kiambu 3,598,902.90
Construction of Thika Bypass 10 Tosha Holdings Commencing Kiambu 1,867,953,057.60

LOW VOLUME SEAL ROADS

PROJECT NAME DISTANCE (Km) CONTRACTOR STATUS  COUNTY COST KSH
Improvement to paved standards of Bomet-Kapsimotwa Road 3 Shovels & Trowels Ltd 50% Bomet 156,208,695.75
Improvement of Lady Irene-Mandizini-Muslim-Nambaya-Junction D258 & Wakili Road 8 Isfahan Contractors Company Ltd 19% Bungoma 118,101,592.14
Improvement to Bitumen Standards of Mokowe Township Roads, Lamu County 15 Nothern Liberty Builders Ltd 14% Lamu 1,115,912,220.75
Improvement of Wote Township Roads 6 Jamkara Contractors Ltd 40% Makueni 348,487,148
Improvement of Maua Town Roads 15 Golden Ruby Investments Ltd 25% Meru 102,188,593,98
Improvement to Bitumen Standards of Nakuru CBD Roads 22 Weihai International Economic & Technical Cooperative Co. Ltd 21% Nakuru      1,815,176,216.74
Upgrading of Hola Township Roads 10  Abdulhakim Ahmed Bayusuf & sons Ltd 45% Tana River          542,113,177.30
Improvement of Kitale Township Roads, Trans-nzoia County-(District Hospital Ndowasco Rd-Showground) 2  Koslam Constructions Ltd 80% Uasin Gishu          164,430,861.30
Improvement to Bitumen Standards of Eldoret Township Roads, Uasin Gishu County 15  Tai Enterprises Ltd 38% Uasin Gishu      1,146,518,437.95
Upgrading and Maintenance of Kapenguria Township Roads 4  Magic Industries Ltd 68% West Pokot          178,863,602.76
Construction To Bitumen Standards of Jomvu Kuu – Jitoni – Rabai Road, Mombasa County 11.7  Associated construction Ltd 6% Mombasa      1,054,897,550.40
Construction of County Road and Garissa Ndogo-Sankuri Link Road, Garissa County 5  Hagar Construction ltd 30% Garissa          480,706,528.80
Improvement to Bitumen Standards of Kapkwen-Kapsimotwa-Silibwet Road, Bomet County 7.4  Subway Construction Ltd 40% Bomet          485,920,536.24
Rehabilitation of Old Malindi Road, Mombasa County Rehabilitation of Old Malindi Road, Mombasa County 13  Equistar Limited 17% Mombasa          796,371,134.40